Solar power plant for the Jraber gas filling station

We have completed one of the unique and complex projects of its kind in Armenia — the solar power plant of the Jraber gas filling station.<br><br>Thanks to the solar power plant, the station achieves annual savings of 33,000,000 AMD by generating 785,700 kWh of electricity.

June 6, 2025
Արևային կայան Ջրաբերի գազալցակայանի համար
Project Location
Republic of Armenia, Kotayk Province, Jraber Village
Standing power
500 kW
Annual productivity
775,000 kWh
Annual savings
33000000 AMD

About the Project

To construct the photovoltaic plant with an installed capacity of 500 kW, it was necessary to overcome several challenges, including the 35° slope of the hillside, the 300-meter distance from the transformer to the plant, the complete absence of a road leading from the gas station to the hillside, as well as a number of other difficulties. However, these obstacles did not prevent us from carrying out our commitment in the best possible way.